Adapt to
changing
situations
and needs
Rail monitoring requirements differ
from project to project and can also
vary within the same project.
Different data acquisition intervals may be required as the project
evolves or starts reaching its end phase. Having an automated
monitoring system that provides results every 30 minutes may not
always be necessary.
For example, after an initial intense period of construction work near
a rail tunnel, a project could transform from high-risk to low-risk and
require different data collection methods. While real-time monitoring
24 hours a day is often required in the beginning of a project,
only semi-automated (also called campaign, periodic and manual)
data collection may be needed at a mature phase.